Quick Answer: Several large data center projects have been announced or proposed in and around Wichita Falls, but as of November 2026 only Google's campus near Vernon is under construction. Skybox's Wichita Falls campus has bought its land and delayed groundbreaking to early 2027. Calvano's site is rezoned but has no announced timeline. Project Raptor in Archer County is still proposed and facing local opposition. And since August 2026, Texas has paused new data center grid approvals and environmental permits while the state audits every project.

Key Takeaways

  • Announced, rezoned, approved, under construction and operating are five different things. Most local projects are in the first three stages.
  • Google's Wilbarger County campus near Vernon is the only regional project under construction.
  • Texas is auditing every data center seeking a grid connection, which has slowed projects statewide, including Skybox.
  • Archer County denied Project Raptor's tax abatement and has opposed its wastewater permits.
  • It's too early to measure any effect on Wichita Falls home values or rents.

Data centers have become one of the biggest economic-development topics in North Texas. In more than three decades in real estate, I've learned that announcements and reality are two different things. At The Debra West Team, our job is to help you separate what has actually happened from what is still proposed. That distinction matters more than any headline.

Why Are Data Centers Looking at Wichita Falls?

Artificial intelligence and cloud computing are driving record demand for data centers, and Texas is a top target. Our region offers available land, major electrical transmission, affordable real estate and a location between Dallas-Fort Worth and Oklahoma City.

The biggest factor is electricity. As of mid-2026, ERCOT was tracking about 474 gigawatts of large-load requests, roughly 90% from data centers. That is more than five times the state's record peak demand, so most of those requests will never be built.

What Is Texas Doing About All These Requests?

Texas has moved from scrutiny to a pause:

  • 2025: Senate Bill 6 set new rules for loads of 75 megawatts or more, including study fees, disclosure of duplicate requests and the ability for ERCOT to curtail large users in emergencies.
  • Aug 3, 2026: Gov. Abbott ordered ERCOT and the PUC to audit every data center seeking a grid connection, covering power, water, cooling, incentives and ownership. ERCOT paused new data center approvals.
  • Sept 21, 2026: TCEQ was directed to suspend data center environmental permits until the audits are finished. In October, the Attorney General's office also sent water-use reporting letters to data center developments in 32 counties, including Wichita County.

On Oct 19, TCEQ confirmed to the governor that it has paused permits directly supporting data centers. ERCOT is scheduled to file its audit reports with the PUC on Dec 10, 2026, and the Legislature returns in January 2027. Which projects get power will likely decide which ones get built.

Which Data Center Projects Are Near Wichita Falls?

Project Location Size Status (Nov 2026)
Skybox PowerCampus Texas Wichita Falls Business Park 300+ acres, up to ~2M sq ft Land sold; groundbreaking delayed to Q1 2027
Calvano Development North Wichita Falls (Kiel Ln / Northwest Fwy) 227 acres, up to 300 MW Rezoned Nov 2024; no timeline announced
DataNovaX 2236 Airport Dr, Wichita Falls ~12 MW conversion of an existing building Approved Aug 2026; air cooling required
Airport Drive rezoning Airport Dr / I-44 9 buildings proposed Rejected by City Council May 5, 2026
Google, Wilbarger County Near Vernon, ~50 miles west Two buildings, ~$1B Under construction since spring 2026
Project Raptor Three Way Rd, Archer County 2,800 acres, up to 1,000 MW Proposed; tax abatement denied; permits opposed
Project Saltworks Near Graham, Young County ~890 acres Early planning; local opposition

What Is Skybox PowerCampus Texas?

Skybox Datacenters, working with investment manager Blue Owl, announced the campus in February 2026. The City approved selling about 225 acres in the business park for more than $14.5 million, the largest land sale in city history, and Skybox holds an option on about 125 more acres.

Skybox says it will use closed-loop cooling, isn't seeking tax abatements and will pay for its own infrastructure. It hasn't published a megawatt figure or named a tenant. On Oct 6, 2026, Skybox told the City Council that groundbreaking is delayed to the first quarter of 2027 because of the state audit, with the first building now expected in late 2028 at the earliest.

Does Rezoning Mean a Data Center Will Be Built?

No. In November 2024 the City Council rezoned about 227 acres in north Wichita Falls for a hyperscale campus tied to Calvano Development. Rezoning only allows the use. Engineering, power, financing and a tenant still have to come together, and no timeline has been announced.

The opposite can happen too. On May 5, 2026, the council unanimously rejected a nine-building data center rezoning near Airport Drive. A smaller conversion of an existing building at 2236 Airport Dr was approved in August 2026, with evaporative cooling prohibited.

What Is Google Building Near Vernon?

Google announced its Wilbarger County campus in February 2026, about 50 miles west of Wichita Falls. What makes it different is that AES is building new power generation and shared electrical infrastructure alongside it under 20-year agreements, rather than relying only on the existing grid. Google says the site uses advanced air cooling, with water limited mainly to uses like kitchens. Construction began in spring 2026, and at an October open house Google said it plans to be in Vernon for the next 30 years.

What Is Project Raptor in Archer County?

Project Raptor is the proposed campus along Three Way Road southwest of Wichita Falls. Information released by Archer County describes:

  • About 2,800 acres and four buildings under the current plan
  • Up to 1,000 megawatts, dependent on ERCOT approval
  • About $1 billion in potential investment
  • Fewer than 1,000 workers at peak construction and about 50 permanent jobs
  • Air-cooled chillers, maximum water use of about 32,000 gallons per day, and a 65 dBA noise target at the property line

Google has been named as the potential developer and operator; the applicant is Dynamo Ventures LLC.

The project has hit resistance. Archer County commissioners unanimously denied its tax abatement on June 22, 2026. Dynamo Ventures has applied to TCEQ to discharge up to 95,000 gallons per day of treated wastewater, and on Sept 28 the county adopted resolutions opposing those permits. Both applications are pending at TCEQ (WQ0017005001 for discharge and WQ0016998001 for on-site evaporation), no public meeting has been scheduled, and with the statewide pause, no decisions are expected soon.

An application is not an approval, and a denied incentive is not a cancelled project. Both are true here.

Frequently Asked Questions

Is a data center being built in Wichita Falls right now?

Not yet. Skybox has bought its land but delayed groundbreaking to early 2027. The only regional project under construction is Google's campus near Vernon.

Is Google building a data center in Archer County?

Google has been named as the potential developer of Project Raptor, but it is still proposed and depends on ERCOT approval and state permits.

Why did Texas pause data center approvals?

ERCOT received far more power requests than the grid can serve. The state is auditing each project's power, water and community impact before approving connections.

Will data centers raise home prices in Wichita Falls?

There isn't enough evidence yet. Part 2 of this series looks at jobs, housing, water and taxes.

Information current as of November 2026. Data center projects, permits and schedules change frequently.

Sources: ERCOT Senate presentation, July 29, 2026 · Texas Tribune, Aug 3, 2026 · TPR, Sept 21, 2026 · Texas Tribune, Oct 20, 2026 · KBTX: AG water-use letters · KAUZ: Skybox delay · DCD: Calvano rezoning · KAUZ: DataNovaX · Google: Wilbarger County · AES · KAUZ: Google open house · Archer County News: Project Raptor FAQ · KAUZ: Archer abatement denied · Archer County News: permit opposition · TCEQ pending applications

Serving Wichita Falls and North Texas

Curious What This Means for Your Property?

Coming next in Part 2: jobs, housing, water, power and taxes.

Talk With Our Team

The Debra West Team | RE/MAX

Categories

Buyer Resources, Home Selling, Wichita Falls Real Estate
Agent profile image in chat bubble
Agent profile image in chat header

Debra West

BROKER | OWNER | The Debra West Team | REMAX Elite Group

Agent profile image in message

or another way